• Baroula Bye Pass, Opp. A.D.A Colony, Aligarh – 202001 (U.P)

project-image
project-image
project-image
project-image
project-image

Re-alignment of pipeline through HDD in 10.75” OD + 4" pipeline at Yamuna River Crossing, Ch 34.2 Km Kurukshetra-Roorkee section of KRNPL

Crossing:-  Yamuna River . 
Ch :- 34.2 KM
Job Length :- 1823 MTR
Strata - Sand with Gravels 
Tracking Device- Mag -9 
Depth :- 32MTR 
Rig- ZT 500Ton
Client:- IOCL
Contractor - M/s Mansi Ganga Builders & Engineers Pvt Ltd.